Rhinelander’s Streetscape construction begins Mar. 28
By Eileen Persike
Editor
The Downtown Rhinelander Streetscape contractors have released a schedule of work and road closures for the week of Mar. 28 through April 1.
Map courtesy of Town & Country Engineers
ROAD CLOSURES -NO VEHICLE TRAFFIC
- Davenport Street bridge
- Davenport Street, from the bridge to Stevens Street
- Intersection of Courtney and Rives Streets
LIMITED CONSTRUCTION ACTIVITY – LOCAL TRAFFIC ONLY
- Courtney Street, Davenport to Young
- Courtney Street, Davenport to Rives
- Scroll down for a map of alternate routes
Scheduled work activities for the week:
Davenport Street, bridge to Courtney
- Asphalt removals
- Storm and sanitary sewer construction, from the river, installing to the east
- Water main construction, from west of Stevens, installing to the west
- WPS installing new gas main
Rives Street, river to east side of Courtney
- Storm Sewer Construction
Courtney Street, Young to Davenport
- WPS installing new gas main